[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145188":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145188,800,2,"多选题","建筑工程施工中，工期索赔的计算方法包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","网络分析法",true,{"key":16,"text":17,"correct":14},"B","比例分析法",{"key":19,"text":20,"correct":21},"C","总费用法",false,{"key":23,"text":24,"correct":21},"D","分项法",{"key":26,"text":27,"correct":21},"E","经验法","AB","2020教材P320 \u002F 2019教材P322 工期索赔的计算算方法：（1）网络分析法：网络分析法通过分析延误前后的施工网络计划，比较两种工期（关键线路）计算结果，计算出工程应顺延的工程工期。（2）比例分析法：比例分析法通过分析增加或减少的单项工程量（工程造价）与合同总量（合同总造价）的比值，推断出增加或减少的工程工期。（3）其他方法：工程现场施工中，可以按照索赔事件实际增加的天数确定索赔的工期；也可通过发包方与承包方协议确定索赔的工期",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]