[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145170":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145170,800,2,"多选题","关于对其他项目费用计算规定的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","计日工应按监理方实际签证确认的事项计算",false,{"key":16,"text":17,"correct":14},"B","总承包服务费应依据合同约定金额计算，如发生调整的，以发包方确认调整金额计算",{"key":19,"text":20,"correct":21},"C","索赔费用应依据发、承包双方确认的索赔事项和金额计算",true,{"key":23,"text":24,"correct":21},"D","现场签证费用应依据发、承包双方签证资料确认的金额计算",{"key":26,"text":27,"correct":14},"E","暂列金额应减去工程价款调整与索赔、现场签证金额计算，如有余额归承包人","CD","2020教材P304 \u002F 2019教材P305 其他项目费通常是按照合同条件规定填报，例如暂列金额。计日工需要单独填报价格即可，用于施工过程中临时发生的雇工费用支出。总包管理费是施工单位自行按照总包范围和总包费率计算而得。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]