[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145163,800,1,"单选题","关于《建设工程工程量清单计价规范》的运用，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A",".非国有资金投资的建设工程，不宜采用工程量清单计价",false,{"key":16,"text":17,"correct":18},"B","分部分项工程和单价措施项目清单应采用综合单价计价",true,{"key":20,"text":21,"correct":14},"C","工程量清单必须作为招标文件的组成部分，其准确性和完整性由投标人负责",{"key":23,"text":24,"correct":14},"D","措施项目清单宜按照下列内容列项：暂列金额、暂估价、计日工、总承包务费C是由招标人负责","2020教材P299 \u002F 2019教材P300 全部使用国有资金投资或国有资金投资为主（以下二者简称国有资金投资）的建设工程施工发承包，必须采用工程量清单计价。非国有资金投资的建设工程，宜采用工程量清单计价。 其他项目清单宜按照下列内容列项：暂列金额、暂估价、计日工、总承包务费",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]