[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145159":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145159,800,2,"多选题","固定单价合同计价方式下综合单价未包含的因素是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","利润",false,{"key":16,"text":17,"correct":14},"B","风险",{"key":19,"text":20,"correct":21},"C","规费",true,{"key":23,"text":24,"correct":14},"D","管理费",{"key":26,"text":27,"correct":21},"E","税金","CE","2020教材P299 \u002F 2019教材P301 分部分项工程费和措施费是指完成一个规定计量单位的分部分项工程量清单项目或措施清单项目所需的人工费、材料费、施工机械使用费和企业管理费与利润，以及一定范围内的风险费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]