[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145156,800,1,"单选题","关于工程量清单主要组成部分的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单、措施项目清单、暂估价材料清单",false,{"key":16,"text":17,"correct":14},"B","分部分项工程量清单、措施项目清单、暂定金额部分清单",{"key":19,"text":20,"correct":21},"C","分部分项工程量清单、措施项目清单、其他项目清单",true,{"key":23,"text":24,"correct":14},"D","分部分项工程量清单、开办费用项目清单","2020教材P299 \u002F 2019教材P301 工程量清单是指建设工程的分部分项工程项目、措施项目、其他项目、规费项目和税金项目的名称和相应数量等的明细清单，是招标文件的组成部分，为潜在的投标者提供必要的信息，需要具有资格的工程造价人员承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]