[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145155,800,1,"单选题","在工程招投标的过程中，投标人完全不应承担的风险为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","技术风险",false,{"key":16,"text":17,"correct":14},"B","管理风险",{"key":19,"text":20,"correct":14},"C","材料价格风险",{"key":22,"text":23,"correct":24},"D","法律、法规变化的风险",true,"2020教材P300 \u002F 2019教材P302 该计价风险不包括：国家法律、法规、规章和政策变化；省级或行业建设主管部门发布的人工费调整；合同中已经约定的市场物价波动范围；不可抗力。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]