[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145150,800,1,"单选题","为了方便投标人组价，需要纳入分部分项工程量清单项目综合单价中的暂估价应是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费和材料费",false,{"key":16,"text":17,"correct":18},"B","材料费",true,{"key":20,"text":21,"correct":14},"C","设备费",{"key":23,"text":24,"correct":14},"D","专业人工费","2020教材P301 \u002F 2019教材P303 材料暂估价应按招标人在其他项目清单中列出的单价计人综合单价；",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]