[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145149":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145149,800,2,"多选题","以工程量清单计价方式投标时，不得作为竞争性费用的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","措施项目清单中的检验及测试费",false,{"key":16,"text":17,"correct":18},"B","措施项目清单中的安全文明施工费",true,{"key":20,"text":21,"correct":18},"C","规费",{"key":23,"text":24,"correct":14},"D","保险",{"key":26,"text":27,"correct":18},"E","税金","BCE","2020教材P301 \u002F 2019教材P303 措施费应根据招标文件中的措施费项目清单及投标时拟定的施工组织设计或施工方案自主确定，但是措施项目清单中的安全文明施工费应按照不低于国家或省级、行业建设主管部门规定标准的90%计价，不得作为竞争性费用。规费和税金应按国家或省级、行业建设主管部门的规定计算，不得作为竞争性费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]