[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145117":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145117,800,2,"多选题","《建筑施工扣件式钢管脚手架安全技术规范》（JGJ 130—2011）规定，脚手架及其地基基础在（ ）后必须进行检查与验收。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","作业层上施加荷载前",true,{"key":16,"text":17,"correct":14},"B","遇有六级及六级以上大风、大雨",{"key":19,"text":20,"correct":14},"C","每搭设完6~8m高度后",{"key":22,"text":23,"correct":14},"D","达到设计高度后",{"key":25,"text":26,"correct":27},"E","停用超过15天",false,"ABCD","2020教材P266 \u002F 2019教材P268 脚手架及其地基基础应在下列阶段进行检查与验收：（1）基础完工后及脚手架搭设前；（2）作业层上施加荷载前；（3）每搭设完6~8m高度后；（4）达到设计高度后；（5）遇有六级大风与大雨后；寒冷地区开冻后；（6）停用超过一个月。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]