[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145112,800,1,"单选题","关于模板拆除的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在设计无规定的时候，底模及其支架拆除应由项目经理决定",false,{"key":16,"text":17,"correct":18},"B","后张法预应力构件侧模宜在预应力张拉前拆除",true,{"key":20,"text":21,"correct":14},"C","后张法预应力构件底模宜在预应力张拉前拆除",{"key":23,"text":24,"correct":14},"D","拆模通常先拆承重部分后拆非承重部分","2020教材P268 \u002F 2019教材P270 3）后张法预应力混凝土结构或构件模板的拆除，侧模应在预应力张拉前拆除，其混凝土强度达到侧模拆除条件即可。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]