[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145109,800,1,"单选题","关于混凝土基础模板及其支撑拆除顺序原则的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先支先拆",false,{"key":16,"text":17,"correct":14},"B","后支后拆",{"key":19,"text":20,"correct":14},"C","顺序拆除",{"key":22,"text":23,"correct":24},"D","先支后拆",true,"2020教材P269 \u002F 2019教材P271 各类模板拆除的顺序和方法，应根据模板设计的要求进行。如果模板设计无要求时，可按：先支的后拆，后支的先拆，先拆非承重的模板，后拆承重的模板及支架的顺序进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]