[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145068,800,1,"单选题","下列质量问题常见成因中，属于管理事故成因的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预埋件偏位",false,{"key":16,"text":17,"correct":14},"B","不均匀沉降",{"key":19,"text":20,"correct":14},"C","防水材料质量不合格",{"key":22,"text":23,"correct":24},"D","分部分项工程施工顺序不当",true,"2020教材P232 \u002F 2019教材P234 8.管理事故（1）分部分项工程施工安排顺序不当，造成质量问题和严重经济损失。（2）施工人员不熟悉图纸，盲目施工，致使构件或预埋件定位错误。（3）在施工过程中未严格按施工组织设计、方案和工序、工艺标准要求进行施工，造成经济失。（4）对进场的材料、成品、半成品不按规定检查验收、存放、复试等，造成经济损失。（5）未尽到总包责任，导致现场出现管理混乱，进而造成一定的经济损失。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]