[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145066,800,1,"单选题","工程质量事故发生后，工程建设单位负责人接到报告后，应于（ ）内向事故发生地有关部门报告出书面报告。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1小时",true,{"key":16,"text":17,"correct":18},"B","2小时",false,{"key":20,"text":21,"correct":18},"C","3小时",{"key":23,"text":24,"correct":18},"D","4小时","2020教材P233 \u002F 2019教材P235 工程质量问题发生后，事故现场有关人员应当立即向工程建设单位负责人报告;工程建设单位负责人接到报告后，应于1h内向事故发生地县级以上人民政府住房和城乡建设主管部门及有关部门报告。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]