[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145050":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145050,800,2,"多选题","土方开挖前，工程质量检查的内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","定位放线",true,{"key":16,"text":17,"correct":14},"B","排水和降低地下水位系统",{"key":19,"text":20,"correct":21},"C","平面位置",false,{"key":23,"text":24,"correct":21},"D","水平标高",{"key":26,"text":27,"correct":21},"E","场地情况","AB","2020教材P225 \u002F 2019教材P227 1A423031地基基础工程质量检查与检验—、土方工程（1）土方开挖前，应检查定位放线、排水和降低地下水位系统。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]