[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145044,800,1,"单选题","下列属于现场土方开挖前应检查的内容是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","定位放线、周围环境和降低地下水位系统",false,{"key":16,"text":17,"correct":14},"B","定位放线、压实度和周围环境",{"key":19,"text":20,"correct":21},"C","定位放线、排水和降低地下水位系统",true,{"key":23,"text":24,"correct":14},"D","定位放线、运输路线和排水降水系统","2020教材P225 \u002F 2019教材P227 一、土石方工程（1）土方开挖前，应检查定位放线、排水和降低地下水位系统。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]