[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145043":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145043,800,1,"单选题","灰土、砂和砂石地基工程施工结束后，应检查其（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承载力",true,{"key":16,"text":17,"correct":18},"B","变形",false,{"key":20,"text":21,"correct":18},"C","含水量",{"key":23,"text":24,"correct":18},"D","标高","2020教材P226 \u002F 2019教材P228 （3）施工结束后，应检验灰土、砂和砂石地基的承载力。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]