[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145036":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145036,800,2,"多选题","灰土地基施工过程中，工程质量应查验的项目有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分层铺设厚度",true,{"key":16,"text":17,"correct":14},"B","夯实时加水量",{"key":19,"text":20,"correct":21},"C","承载力",false,{"key":23,"text":24,"correct":14},"D","压实系数",{"key":26,"text":27,"correct":14},"E","夯压遍数","ABDE","2020教材P226 \u002F 2019教材P228 施工过程中应检查分层铺设的厚度、分段施工时上下两层的搭接长度、夯实时加水量、夯压遍数、压实系数。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]