[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145035,800,2,"多选题","打（压）桩工程施工结束后，下列检查项目中（ ）几项必须符合设计要求及规范规定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","桩身垂直度",false,{"key":16,"text":17,"correct":18},"B","承载力检测",true,{"key":20,"text":21,"correct":14},"C","桩身贯人度",{"key":23,"text":24,"correct":18},"D","竣工位置偏差",{"key":26,"text":27,"correct":18},"E","桩身完整性检测","BDE","2020教材P226 \u002F 2019教材P228 桩竣工位置偏差、桩身完整性检测和承载力检测必须符合设计要求和规范规定。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]