[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145022,800,1,"单选题","厕浴间、厨房防水层完工后，应做（ ）蓄水试验。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8h",false,{"key":16,"text":17,"correct":14},"B","12h",{"key":19,"text":20,"correct":21},"C","24h",true,{"key":23,"text":24,"correct":14},"D","48h","2020教材P229 \u002F 2019教材P231 厨房、厕浴间防水层完成后，应做24h蓄水试验，确认无渗漏时再做保护层和面层。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]