[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145020,800,1,"单选题","关于室内地面防水施工质量验收程序的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基层→防水层→蓄水试验→保护层→面层→验收",false,{"key":16,"text":17,"correct":14},"B","基层→防水层→保护层→面层→蓄水试验→验收",{"key":19,"text":20,"correct":14},"C","基层→防水层→蓄水试验→二次蓄水试验→保护层→面层→验收",{"key":22,"text":23,"correct":24},"D","基层→防水层→蓄水试验→保护层→面层→二次蓄水试验→验收",true,"2020教材P229 \u002F 2019教材P231 此题考察防水施工质量验收程序。（三）厨房、厕浴间防水工程厨房、厕浴间防水层完成后，应做24h蓄水试验，确认无渗漏时再做保护层和面层。设备与饰面层施工完后还应在其上继续做第二次24h蓄水试验，达到最终无渗漏和排水畅通为合格，方可进行正式验收。墙面间歇淋水试验应达到30min以上不渗漏。得出：防水层-蓄水试验-保护层-面层-二次蓄水试验-验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]