[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145019,800,1,"单选题","检查屋面是否有渗漏、积水和排水系统是否畅通，应在雨后或持续淋水（ ）h后进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","12",{"key":23,"text":24,"correct":18},"D","24","2020教材P229 \u002F 2019教材P231 防水层完工后，应在雨后或持续淋水2h后（有可能做蓄水试验的屋面，其蓄水时间不应少于24h）,检查屋面有无渗漏、积水和排水系统是否畅通，施工质量符合要求方可进行防水层验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]