[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144995,800,1,"单选题","材料进场时，应提供材质证明，并根据供料计划和有关标准进行现场质量抽检和记录，试验结果报（ ）审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目物资主管工程师",false,{"key":16,"text":17,"correct":14},"B","项目质量主管工程师",{"key":19,"text":20,"correct":21},"C","项目监理工程师",true,{"key":23,"text":24,"correct":14},"D","建设单位项目负责人","2020教材P224 \u002F 2019教材P226 材料进场时，应提供材料或产品合格证，并根据供料计划和有关标准进行现场质量验证和记录。质量验证包括材料品种.型号.规格.数量.外观检查和见证取样。验证结果记录后报监理工程师审批备案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]