[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144992,800,2,"多选题","建筑材料质量控制的主要过程有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","检验",true,{"key":16,"text":17,"correct":14},"B","采购",{"key":19,"text":20,"correct":14},"C","保管",{"key":22,"text":23,"correct":14},"D","使用",{"key":25,"text":26,"correct":27},"E","保修",false,"ABCD","2020教材P224 \u002F 2019教材P226 建筑材料的质量控制主要体现在以下四个环节：材料的采购、材料进场试验检验、过程保管和材料使用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]