[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144976,800,1,"单选题","项目质量管理程序的第一步是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收集分析质量信息并制定预防措施",false,{"key":16,"text":17,"correct":14},"B","编制项目质量计划",{"key":19,"text":20,"correct":21},"C","明确项目质量目标",true,{"key":23,"text":24,"correct":14},"D","实施项目质量计划","2020教材P221 \u002F 2019教材P223 项目质量管理应遵循的程序：（1)明确项目质量目标；（2)编制项目质量计划；(3)实施项目质量计划；（4)监督检查项目质量计划的执行情况；（5)收集、分析、反馈质量信息并制定预防和改进措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]