[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144975,800,1,"单选题","建筑工程项目质量管理的首要步骤是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制项目质量计划",false,{"key":16,"text":17,"correct":18},"B","明确项目质量目标",true,{"key":20,"text":21,"correct":14},"C","项目各阶段的质量控制",{"key":23,"text":24,"correct":14},"D","对项目质量管理工作制定预防和改进措施","2020教材P221 \u002F 2019教材P223 项目质量管理应遵循的程序：（1）明确项目质量目标；(2)编制项目质量计划；(3)实施项目质量计划；(4)监督检查项目质量计划的执行情况；(5)收集.分析.反馈质量信息并制定预防和改进措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]