[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144973":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144973,800,2,"多选题","下列进度计划中，宜优先采用网络图表示的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划",true,{"key":16,"text":17,"correct":18},"B","小型单位工程施工进度计划",false,{"key":20,"text":21,"correct":18},"C","中型单位工程施工进度计划",{"key":23,"text":24,"correct":14},"D","大型单位工程施工进度计划",{"key":26,"text":27,"correct":14},"E","工序复杂的工程施工进度计划","ADE","2020教材P219 \u002F 2019教材P221 施工总进度计划可采用网络图或横道图表示，并附必要说明，宜优先采用网络计划。压轴卷，考前会在金考典考试软件更新哦~ 软件下载链接www.jinkaodian.com单位工程施工进度计划一般工程用横道图表示即可，对于工程规模较大、工序比较复杂的工程宜采用网络图表示，通过对各类参数的计算，找出关键线路，选择最优方案。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]