[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144972":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144972,800,2,"多选题","关于施工总进度计划特点的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","作业性较强",false,{"key":16,"text":17,"correct":18},"B","控制性较强",true,{"key":20,"text":21,"correct":18},"C","综合性较强",{"key":23,"text":24,"correct":14},"D","可操作性强",{"key":26,"text":27,"correct":14},"E","包含内容明确","BC","2020教材P216 \u002F 2019教材P218 施工总进度计划由于施工的内容较多，施工工期较长，故其计划项目综合性强，较多关注控制性，很少关注作业性。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]