[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144971":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144971,800,2,"多选题","下列文件中，属单位工程进度计划应包括的内容有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程建设概况",true,{"key":16,"text":17,"correct":18},"B","建设单位可能提供的条件和水电供应情况",false,{"key":20,"text":21,"correct":18},"C","施工现场条件和勘察资料",{"key":23,"text":24,"correct":14},"D","分阶段进度计划",{"key":26,"text":27,"correct":14},"E","主要施工方案及流水段划分","ADE","2020教材P218 \u002F 2019教材P220 单位工程进度计划的内容一般应包括：(1)工程建设概况：拟建工程的建设单位，工程名称、性质、用途、工程投资额，开竣工日期，施工合同要求，主管部门和有关部门的文件和要求以及组织施工的指导思想等。(2)工程施工情况：拟建工程的建筑面积、层数、层高、总高、总宽、总长、平面形状和平面组合情况，基础、结构类型，室内外装修情况等。(3)单位工程进度计划，分阶段进度计划，单位工程准备工作计划，劳动力需用量计划，主要材料、设备及加工计划，主要施工机械和机具需要量计划，主要施工方案及流水段划分，各项经济技术指标要求等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]