[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144970,800,2,"多选题","关于项目单位工程施工进度计划编制步骤包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分解单项工程，列出每个单项工程的单位工程和每个单位工程的分部工程",false,{"key":16,"text":17,"correct":18},"B","确定施工顺序",true,{"key":20,"text":21,"correct":18},"C","计算工程量",{"key":23,"text":24,"correct":18},"D","计算劳动量或机械台班需用量",{"key":26,"text":27,"correct":18},"E","收集编制依据","BCDE","2020教材P219 \u002F 2019教材P221 2.单位工程进度计划的编制步骤(1)收集编制依据；(2)划分施工过程、施工段和施工层；(3)确定施工顺序；(4)计算工程量；(5)计算劳动量或机械台班需用量；(6)确定持续时间；(7)绘制可行的施工进度计划图；(8)优化并绘制正式施工进度计划图。 A是施工总进度计划编制的内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]