[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144969":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144969,800,1,"单选题","项目进度控制的目标为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实现合同约定的竣工日期",true,{"key":16,"text":17,"correct":18},"B","编制施工进度计划",false,{"key":20,"text":21,"correct":18},"C","申请开工并按指令日期开工",{"key":23,"text":24,"correct":18},"D","进度控制总结并编写施工进度控制报告","2020教材P219 \u002F 2019教材P221 项目进度控制的目标就是确保项目按既定工期目标实现，或在实现项目目标的前提下适当缩短工期。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]