[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144967":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144967,800,2,"多选题","施工进度计划的检查方法主要有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","横道计划法",true,{"key":16,"text":17,"correct":14},"B","网络计划法",{"key":19,"text":20,"correct":21},"C","函询调查法",false,{"key":23,"text":24,"correct":14},"D","S形曲线法",{"key":26,"text":27,"correct":14},"E","实际进度前锋线法","ABDE","2020教材P220 \u002F 2019教材P222 施工进度计划实施监测的方法有：横道计划比较法，网络计划法，实际进度前锋线法，S形曲线法，香蕉型曲线比较法等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]