[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144964":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144964,800,2,"多选题","组织流水施工时，如果按专业成立专业工作队，则其特点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各专业队在各施工段均可组织流水施工",true,{"key":16,"text":17,"correct":18},"B","只有一个专业队在各施工段组织流水施工",false,{"key":20,"text":21,"correct":14},"C","各专业队可按施工顺序实现最大搭接",{"key":23,"text":24,"correct":14},"D","有利于提高劳动生产效率和工程质量",{"key":26,"text":27,"correct":18},"E","同一时间段只能有一个专业队投入流水施工","ACD","2020教材P208 \u002F 2019教材P210 流水施工的特点：（1）科学利用工作面，争取时间，合理压缩工期；（2）工作队实现专业化施工，有利于工作质量和效率的提升；（3）工作队及其工人、机械设备连续作业，同时使相邻专业工作队的开工时间能够最大限度地搭接，减少窝工和其他支出，降低建造成本；（4）单位时间内资源投人量较均衡，有利于资源组织与供给。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]