[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144963":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144963,800,2,"多选题","关于组织流水施工所需条件的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程项目划分为工程量大致相等的施工段",true,{"key":16,"text":17,"correct":14},"B","工程项目分解为若干个施工过程",{"key":19,"text":20,"correct":21},"C","组织尽量多的施工队，并确定各专业队在各施工段的流水节拍",false,{"key":23,"text":24,"correct":14},"D","不同专业队完成各施工过程的时间适当搭接起来",{"key":26,"text":27,"correct":14},"E","各专业队连续作业","ABDE","2020教材P208 \u002F 2019教材P210 流水施工是将拟建工程划分为若干施工段，并将施工对象分解为若干个施工过程，按施工过程成立相应工作队，各工作队按施工过程顺序依次完成施工段内的施工过程，并依次从一个施工段转到下一个施工段；施工在各施工段、施工过程上连续、均衡地进行，使相应专业工作队间最大限度地实现搭接施工。施工队数量应按施工过程进行组织，并不是越多越好，故C不正确。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]