[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144962,800,2,"多选题","组织流水施工时，划分施工段的主要目的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可增加更多的专业队",false,{"key":16,"text":17,"correct":18},"B","有利于各专业队在各施工段组织流水施工",true,{"key":20,"text":21,"correct":18},"C","有利于不同专业队同一时间内在各施工段平行施工",{"key":23,"text":24,"correct":14},"D","缩短施工工艺与组织间歇时间",{"key":26,"text":27,"correct":18},"E","充分利用工作面、避免窝工，有利于缩短工期","BCE","2020教材P208 \u002F 2019教材P210 一般情况下，一个施工段内只安排一个施工过程的专业工作队进行施工，在一个施工段上，只有前一个施工过程的工作队提供足够的工作面，后一个施工过程的工作队才能进入该段从事下一个施工过程的施工。所以划分施工段并不能增加更多的专业队，故A不正确。施工工艺时间与组织间歇时间与施工段的划分无直接关系，需结合具体情况才能优化处理，故D不正确。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]