[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144957,800,2,"多选题","下列属于流水施工时间参数的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":18},"B","流水段数",false,{"key":20,"text":21,"correct":14},"C","流水节拍",{"key":23,"text":24,"correct":14},"D","流水步距",{"key":26,"text":27,"correct":18},"E","施工过程数","ACD","2020教材P209 \u002F 2019教材P211 时间参数：指在组织流水施工时，用以表达流水施工在时间安排上所处状态的参数，主要包括流水节拍、流水步距和流水施工工期等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]