[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144951":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144951,800,2,"多选题","关于等步距异节奏流水施工特点的说法，错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各施工过程在同一施工流水段上流水节拍相等",true,{"key":16,"text":17,"correct":14},"B","相邻施工过程之间的流水步距不相等",{"key":19,"text":20,"correct":21},"C","同一施工过程在各施工流水段上流水节拍相等",false,{"key":23,"text":24,"correct":14},"D","专业工作队数目与施工过程数目相等",{"key":26,"text":27,"correct":14},"E","各施工过程间可能有间歇时间","ABDE","2020教材P210 \u002F 2019教材P212 等步距异节奏流水施工特点：（1）同一施工过程在其各个施工段上的流水节拍均相等，不同施工过程的流水节拍不等，其值为倍数关系；（2）相邻施工过程的流水步距相等，且等于流水节拍的最大公约数；（3）专业工作队数大于施工过程数，部分或全部施工过程按倍数增加相应专业工作队;（4）各个专业工作队在各施工段上能够连续作业，各施工过程间没有间隔时间。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]