[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144943,800,1,"单选题","在工程网络计划执行过程中，若某项工作比原计划拖后，而未超过该工怍的自由时差，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不影响总工期，影响后续工作",false,{"key":16,"text":17,"correct":14},"B","不影响后续工作，影响总工期",{"key":19,"text":20,"correct":21},"C","对总工期及后续工作均不影响",true,{"key":23,"text":24,"correct":14},"D","对总工期及后续工作均有影响","2020教材P213 \u002F 2019教材P215 工作自由时差，是指在不影响其所有紧后工作最早开始的前提下，本工作可以利用的机动时间。未超过该工作的自由时差，则不影响该工作的最早开始时间，即对后续工作均不影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]