[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144942,800,1,"单选题","在某工程双代号网络计划中，如果以关键节点为完成节点的工作有3项，则该3项工作（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差相等",false,{"key":16,"text":17,"correct":14},"B","总时差相等",{"key":19,"text":20,"correct":14},"C","全部为关键工作",{"key":22,"text":23,"correct":24},"D","至少有一项为关键工作",true,"2020教材P213 \u002F 2019教材P215 工作自由时差一节点最早时间一该工作最早完成时间，工作总时差一节点的最迟时间一该工作的最早完成时间。但3项工作的最早完成时间不一定相等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]