[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144940,800,2,"多选题","在工程网络计划的执行过程中，关于需要调整原进度计划情况的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目总工期不允许拖延，但工作进度偏差已超过其总时差",true,{"key":16,"text":17,"correct":18},"B","项目总工期允许拖延，但工作进度偏差已超过其自由时差",false,{"key":20,"text":21,"correct":14},"C","后续工作不允许拖延，但工作进度偏差已超过其总时差",{"key":23,"text":24,"correct":18},"D","后续工作允许拖延，但工作进度偏差已超过其自由时差",{"key":26,"text":27,"correct":14},"E","项目总工期允许拖延的时间有限，但实际拖延的时间已超过此限制","ACE","2020教材P213 \u002F 2019教材P215 工作总时差是指在不影响总工期的前提下本工作可以利用的机动时间；工作自由时差是指在不影响其所有紧后工作最早开始的前提下，本工作可以利用的机动时间。所以只要超过总时差肯定影响工期",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]