[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144939,800,1,"单选题","在工程网络计划的执行过程中，如果需要判断某工作进度偏差对总工期是否造成影响，应根据（ ）的差值确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时差与进度偏差",false,{"key":16,"text":17,"correct":18},"B","总时差与进度偏差",true,{"key":20,"text":21,"correct":14},"C","自由时差与总时差",{"key":23,"text":24,"correct":14},"D","自由时差与进度偏差","2020教材P213 \u002F 2019教材P215 时差可分为总时差和自由时差两种：工作总时差，是指在不影响总工期的前提下，本工作可以利用的机动时间；工作自由时差，是指在不影响其所有紧后T作最早开始的前提下，本工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]