[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144938,800,1,"单选题","在工程网络计划中，某工作的最迟完成时间与其最早完成时间的差值是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作的自由时差",false,{"key":16,"text":17,"correct":18},"B","该工作的总时差",true,{"key":20,"text":21,"correct":14},"C","该工作的持续时间",{"key":23,"text":24,"correct":14},"D","该工作与其紧后工作之间的时间间隔","2020教材P213 \u002F 2019教材P215 时差可分为总时差和自由时差两种：工作总时差，是指在不影响总工期的前提下，本工作可以利用的机动时间；工作自由时差，是指在不影响其所有紧后工作最早开始的前提下，本工作可以利用的机动时间",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]