[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144936,800,1,"单选题","当计算工期不能满足合同要求时，应首先压缩（ ）的持续时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键工作",true,{"key":16,"text":17,"correct":18},"B","非关键工作",false,{"key":20,"text":21,"correct":18},"C","总时差最长的工作",{"key":23,"text":24,"correct":18},"D","持续时间最长的工作","教2020教材P214 \u002F 2019教材P216 工期优化也称时间优化，其目的是当网络计划计算工期不能满足要求工期时，通过不断压缩关键线路上的关键工作的持续时间等措施，达到缩短工期、满足要求的目的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]