[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144935,800,1,"单选题","在工程网络计划的工期优化过程中，在缩短工怍持续时间对质量和安全影响不大的情况下，应选择的压缩对象是（ ）的关键工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","持续时间最长且资源消耗最少",false,{"key":16,"text":17,"correct":18},"B","缩短持续时间所需增加费用最少",true,{"key":20,"text":21,"correct":14},"C","持续时间最长且有充足备用资源",{"key":23,"text":24,"correct":14},"D","资源消耗少从而使直接费用最少","教2020教材P214 \u002F 2019教材P216 工期优化也称时间优化，其目的是当网络计划计算工期不能满足要求工期时，通过不断压缩关键线路上的关键工作的持续时间等措施，达到缩短工期、满足要求的目的。选择优化对象应考虑下列因素：（1）缩短持续时间对质量和安全影响不大的工作；（2）有备用资源的工作；;（3）缩短持续时间所需增加的资源、费用最少的工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]