[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144934,800,1,"单选题","在工程网络计划中，判别关键工作的条件是（ ）最小。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差",false,{"key":16,"text":17,"correct":18},"B","总时差",true,{"key":20,"text":21,"correct":14},"C","持续时间",{"key":23,"text":24,"correct":14},"D","时间间隔","教2020教材P214 \u002F 2019教材P216 关键工作：是网络计划中总时差最小的工作，在双代号时标网络图上，没有波形线的工作即为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]