[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144933":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144933,800,2,"多选题","当工程网络计划的计划工期等于计算工期时，关于工程网络计划关键线路的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","双代号网络计划中由关键节点组成",false,{"key":16,"text":17,"correct":18},"B","双代号时标网络计划中没有波形线",true,{"key":20,"text":21,"correct":18},"C","双代号网络计划中总持续时间最长",{"key":23,"text":24,"correct":18},"D","时标网络计划中没有波形线",{"key":26,"text":27,"correct":18},"E","单代号搭接网络计划中相邻工作时间间隔均为零","BCDE","教2020教材P214 \u002F 2019教材P216 关键工作：是网络计划中总时差最小的工作。在双代号时标网络图上，没有波形线的工作即为关键工作。关键线路：全部由关键工作所组成的线路就是关键线路。关键线路的工期即为网络计划的计算工期。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]