[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144932,800,2,"多选题","在工程网络计划中，关键工作是（ ）的工作。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","总时差最小",true,{"key":16,"text":17,"correct":14},"B","关键线路上",{"key":19,"text":20,"correct":21},"C","自由时差为零",false,{"key":23,"text":24,"correct":21},"D","持续时间最长",{"key":26,"text":27,"correct":21},"E","两端节点为关键节点","AB","教2020教材P214 \u002F 2019教材P216 关键工作：是网络计划中总时差最小的工作。在双代号时标网络图上，没有波形线的工作即为关键工作。关键线路：全部由关键工作所组成的线路就是关键线路。关键线路的工期即为网络计划的计算工期。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]