[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144930,800,1,"单选题","在网络计划工期优化过程中，当出现多条关键线路时，在考虑对质量、安全影响的基础上，优先选择的压缩对象应是各条关键线路上（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缩短持续时间所需增加的资源、费用最多的工作",false,{"key":16,"text":17,"correct":18},"B","缩短持续时间对质量和安全影响不大的工作",true,{"key":20,"text":21,"correct":14},"C","缩短持续时间对质量影响大的工作",{"key":23,"text":24,"correct":14},"D","缩短持续时间对安全影响大的工作","教2020教材P214 \u002F 2019教材P216 选择优化对象应考虑下列因素:（1）缩短持续时间对质量和安全影响不大的工作;（2）有备用资源的工作;（3）缩短持续时间所需增加的资源、费用最少的工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]