[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144928,800,1,"单选题","已知某写字楼工程双代号网络计划的计划工期等于计算工期，且工作F的完成节点为关键节点，则该工作（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","为关键工作",false,{"key":16,"text":17,"correct":14},"B","自由时差小于总时差",{"key":19,"text":20,"correct":14},"C","自由时差为零",{"key":22,"text":23,"correct":24},"D","自由时差等于总时差",true,"2020教材P215\u002F 2019教材P217 工作F的完成节点为关键节点，则此节点的最早时间与最迟时间相等，工作F的总时差等于节点的最迟时间减去工作F的最早完成时间；该工作的自由时差等于节点的最早时间减去工作F的最早完成时间，故在数值上是相等的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]