[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144926":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144926,800,1,"单选题","基坑土方回填时，施工过程质量检测试验的项目通常不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承载力",true,{"key":16,"text":17,"correct":18},"B","最优含水量",false,{"key":20,"text":21,"correct":18},"C","压实系数",{"key":23,"text":24,"correct":18},"D","最大干密度","2020教材P193 \u002F 2019教材P195 见表格施工过程质量检测试验的主要内容见表1A421061，最大干密度、最优含水量、压实系数",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]