[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144902,800,1,"单选题","关于冬期建筑装饰装修工程施工的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","室内抹灰，块料装饰工程施工与养护期间的温度不应低于0℃",false,{"key":16,"text":17,"correct":18},"B","油漆、刷浆、裱糊、玻璃工程，室外施工时，其最低环境温度不应低于5℃",true,{"key":20,"text":21,"correct":14},"C","室外喷、涂，刷油漆、高级涂料时，料浆使用温度宜保持5℃左右",{"key":23,"text":24,"correct":14},"D","塑料门窗当在不大于0℃的环境中存放时，与热源的距离不应小于0.5m","2020教材P199 \u002F 2019教材P201 8.建筑装饰装修工程(1)室内抹灰，块料装饰工程施工与养护期间的温度不应低于5℃。(2)油漆、刷浆、裱糊、玻璃工程应在采暖条件下进行施工。当需要在室外施工时，其最低环境温度不应低于5℃。(3)室外喷、涂，刷油漆、高级涂料时应保持施工均衡。粉桨类料浆宜采用热水配制，随用随配并应将料浆保温，料浆使用温度宜保持15℃左右。(4)当存放塑料门窗的环境温度为5℃以下时，安装前应在室温不低于15℃的环境下放置24h。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]